Publications




Search Construction Advisor Today


  • constructionadvisortoday.com

Bookmark and Share

« LEED Update Includes New Requirements for Accredited Professionals | Main | Straw Bale Construction »

07/30/2009

Comments

Feed You can follow this conversation by subscribing to the comment feed for this post.

Bruce, I've described a very detailed method and provided an actual case study demonstrating how to apportion delays amongst multiple parties, and along parallel critical paths, in chapter 6 of "Delay Analysis in Construction Contracts." (Wiley-Blackwell, 2008)

Regards,

Tony Caletka

can you provide a citation to the case. Thanks.

I haven't had a chance to look at Mr. Caletka's "Delay Anaylsis" chapter yet, but it sounds like a good source of information. Thanks. The citation to the case follows.

Appeal of ADT Construction Group, Inc.
Armed Services Board of Contract Appeals, No. 55307 (July 9, 2009)

Owner has a case of CR(Cranial Rectitus). 100 % plans prior to commencement with construction is completely counterintuitive to the spirit & intent of the Design/Build process. Fast tracking/integation of design into the construction process being central to the spirit & intent of a proactive alternate contracting method(than Des-Bid-Build).

CPM should help with extraction of cranium. If all accepted/bought into a CPM, any impacts can be evaluluated. Then players can move on to causation & apportioning. KEY here is having a scheudle tool with bi-lateral acceptance & credibity which all activities & impacts can be accurately represented & measured.

KEY to credibility is ALL believing CPM accurately reflects an ACTUALLY DEVELOPED and CONSIDERED IN BUDGET & WORK COORDINATION PRECONSTRUCTION PLAN to accomplish the work. THen any changes to this plan can be accurately relected & overall completion projections & resutling changes/impacts(good, bad or indifferent) can be bi-laterally agreed to.

This was not a fast-track project if no construction could be done before the design was complete. As far as delays to the project, was the As-Planned schedule based on fast tracking the project and the government changed the requirement for 100% design or was the requirement for 100% always part of the contract?

Well don't know whats going on but its not a Good way to do this. in my opinion we have to look again about this issue

Verify your Comment

Previewing your Comment

This is only a preview. Your comment has not yet been posted.

Working...
Your comment could not be posted. Error type:
Your comment has been posted. Post another comment

The letters and numbers you entered did not match the image. Please try again.

As a final step before posting your comment, enter the letters and numbers you see in the image below. This prevents automated programs from posting comments.

Having trouble reading this image? View an alternate.

Working...

Post a comment